HVAC, controls, equipment startup, TAB support, closeout documentation
| Requirement | Spec | Due | Files | Status | Actions |
|---|---|---|---|---|---|
O&M Manuals O&M Manuals required per spec section 23 05 00. | 23 05 00 | 1969-12-11 | ๐ O_M_Manuals.pdf | Satisfied | |
Warranties Warranties required per spec section 23 05 00. | 23 05 00 | 1969-12-18 | ๐ Warranties.pdf | Satisfied | |
Product Data Product Data required per spec section 23 05 00. | 23 05 00 | 1969-12-25 | ๐ Product_Data.pdf | Satisfied | |
As-Built Markups As-Built Markups required per spec section 23 05 00. | 23 05 00 | 1970-01-01 | ๐ As_Built_Markups.pdf | Uploaded | |
Testing Reports Testing Reports required per spec section 23 05 00. | 23 05 00 | 1970-01-08 | ๐ Testing_Reports.pdf | Pending CORE Review | |
Inspection Reports Inspection Reports required per spec section 23 05 00. | 23 05 00 | 1970-01-15 | None | Open | |
Training Documentation Training Documentation required per spec section 23 05 00. | 23 05 00 | 1970-01-22 | None | Due Soon | |
Attic Stock / Spare Parts Attic Stock / Spare Parts required per spec section 23 05 00. | 23 05 00 | 1970-01-29 | None | Past Due | |
Final Cleaning Documentation Final Cleaning Documentation required per spec section 23 05 00. | 23 05 00 | 1970-02-05 | None | Rejected / Needs Revision | |
Commissioning Documentation Commissioning Documentation required per spec section 23 05 00. | 23 05 00 | 1970-02-12 | ๐ Commissioning_Documentation.pdf | Satisfied |